Fine Bubble diffused aeration (FBDA) contract and ancillary works
Birr WWTP was constructed in 1989 and has a design P.E. of 12,000. The plant consists of inlet works with archimedean screw pumps, inlet screening and degritting facilities, two aeration tanks each with a working capacity of 1,483 m3, two clarifiers and two picket fence thickeners. Aeration in each aeration tank was provided by 1 xNo. 30kW vertical surface rotor driven by 30 kW Danfoss variable speed drives which were controlled by the dissolved oxygen setpoint in each tank.[separator style_type=”single” top_margin=”10″ bottom_margin=”20″ sep_color=”#eaeaea” border_size=”” icon=”” icon_circle=”” icon_circle_color=”” width=”” alignment=”center” class=”” id=””]
Aeration Tank Details
No. of Aeration Tank: 2
Top of Tank Wall (mOD): 46.5
Operational TWL (mOD): 45.25
Tank Floor Level (mOD): 41.35
Tank Depth (meters): 3.9
Cell Length (meters): 19.5
Cell Width (meters): 19.5
Volume m3 per tank: 1483
The scope of the FBDA project included the following main elements of work:
- Removal of existing surface aerators in each of the two tanks
- Fully functional fine bubble diffused aeration (FBDA) system on stainless steel removable grids
- Stainless steel piping
- Three Aerzen D24S Hybrid positive displacement air blowers were installed (Duty Tank No.1/Duty Tank No.2 with 1xNo. common standby)
- Two no. VSDs for existing RAS pumps
- Mechanical and electrical installation
- Adjustments to existing electrical system to cater for new FBDA system
- Installation of power metering
- Testing and commissioning
The aeration system installed utilised the Aquaconsult AEROSTRIP diffusers mounted on liftout grids with an intelligent control system to alternately switch on and off as required.
[separator style_type=”single” top_margin=”10″ bottom_margin=”20″ sep_color=”#eaeaea” border_size=”” icon=”” icon_circle=”” icon_circle_color=”” width=”” alignment=”center” class=”” id=””]
Ancillary Works
In addition to the FBDA contract, Conway Engineering also completed the following ancillary works:
- Refurbishment of step screen to put back into operation, mechanical and electrical installation of same.
- Removal of existing stairs and handrailing to replace with triple height to 1200mm hand railing and new stairs so as to adhere to H&S regulations.